Daily targets for the crew. The blue block on each day is straight from the
production schedule; the checkboxes below it are the
extra goals Kenny assigns. Check a goal when it's DONE - it syncs to everyone's phone.
STAGE RIGHT full install: drill holes, mount LED to NL8 plates, install plates. Goal: Stage Right complete by end of day. CENTER SR HALF: holes drilled.
Gear / RTV / Scenic: Lighting dimmer racks arrive on site. Ryan Cavin arrives with RTV silicone supplies. RTV team (Curtis + Ryan): silicone every ready zone - Stage Left AND Stage Right - and keep moving as far ahead as possible.
SundayJul 12Potential call 7:00 AM
PER PRODUCTION SCHEDULE
CENTER SR HALF: LED to plates, plates installed, siliconed - complete through silicone. CENTER SL HALF: started - holes drilled. RTV: keep moving as far ahead as possible on any ready zone.
Gear / RTV / Scenic: Scenic hard coats behind installed plates as sections free up.
No extra goals assigned - follow the production schedule plan above.
MondayJul 13Potential call 7:00 AM
PER PRODUCTION SCHEDULE
CENTER SL HALF: LED to plates, plates installed, siliconed - complete through silicone.
No extra goals assigned - follow the production schedule plan above.
TuesdayJul 14Potential call 7:00 AM
PER PRODUCTION SCHEDULE
Tie up loose ends: control online and tested, all cables run, loomed, and labeled. Final tidy + punch list.
No extra goals assigned - follow the production schedule plan above.