Daily targets for the crew. The blue block on each day is straight from the
production schedule ; the checkboxes below it are the
extra goals Kenny assigns. Check a goal when it's DONE - it syncs to everyone's phone.
Saturday night Jul 11-12
Overnight
PER PRODUCTION SCHEDULE
-
Gear / RTV / Scenic: Scenic hard coating STAGE RIGHT + STAGE LEFT overnight into Sunday morning.
No extra goals assigned - follow the production schedule plan above.
Sunday Jul 12
Lobby call 7:00 AM
PER PRODUCTION SCHEDULE
CENTER: holes drilled, NL8 plates installed. STAGE RIGHT: RTV silicone finished.
No extra goals assigned - follow the production schedule plan above.
Monday Jul 13
Potential call 7:00 AM
PER PRODUCTION SCHEDULE
CENTER: LED soldered to NL8 cable leads. RTV silicone started, 50% done. Get control dialed in.
No extra goals assigned - follow the production schedule plan above.
Tuesday Jul 14
Potential call 7:00 AM
PER PRODUCTION SCHEDULE
Finish RTV silicone on CENTER. Tie up loose ends. Handover to touring team.
Work the CLOSEOUT PUNCHLIST (button on the hub) Main goals: Solder Crew (Tanner P + Harper) - solder LED to unhardened CSL pieces. RTV Crew (Curt + Ryan) - silicone all of CSL, top down. Nathan - band riser RGBW rewire (check Advatek remap first) + Plates TLC with Tanner L. TOP PRIORITY