Live install status - checkboxes sync to everyone's phone (and to Kenny). Check a box when a
milestone is DONE. The day tag on an unchecked box is the GOAL day - change it with the dropdown if the plan moves.
Call times are potential; end times are play-it-by-ear and never posted.
STAGE LEFT IS READY FOR SCENIC HARD COAT. Holes drilled, LED mounted to NL8 plates, plates installed - no KG3 dependency remains. Scenic can hard coat at any time.
LIGHTING: Sam has the full DMX patch and the map of general zones.
STAGE RIGHT full install: drill holes, mount LED to NL8 plates, install plates. Goal: Stage Right complete by end of day. CENTER SR HALF: holes drilled.
Lighting dimmer racks arrive on site. Ryan Cavin arrives with RTV silicone supplies. RTV team (Curtis + Ryan): silicone every ready zone - Stage Left AND Stage Right - and keep moving as far ahead as possible.
SundayJul 12Potential call 7:00 AM
CENTER SR HALF: LED to plates, plates installed, siliconed - complete through silicone. CENTER SL HALF: started - holes drilled. RTV: keep moving as far ahead as possible on any ready zone.
Scenic hard coats behind installed plates as sections free up.
MondayJul 13Potential call 7:00 AM
CENTER SL HALF: LED to plates, plates installed, siliconed - complete through silicone.
-
TuesdayJul 14Potential call 7:00 AM
Tie up loose ends: control online and tested, all cables run, loomed, and labeled. Final tidy + punch list.